Kementerian Energi Godok Tiga Opsi Lokasi Kilang Proyek Masela Ada beb翻訳 - Kementerian Energi Godok Tiga Opsi Lokasi Kilang Proyek Masela Ada beb英語言う方法

Kementerian Energi Godok Tiga Opsi

Kementerian Energi Godok Tiga Opsi Lokasi Kilang Proyek Masela

Ada beberapa pertimbangan pemilihan lokasi kilang tersebut, seperti aspek teknikal, dapat membangun pabrik petrokimia, sudah berpenghuni, dan memenuhi keekonomian.

Kementerian Energi dan Sumber Daya Mineral (ESDM) tengah membahas lokasi pembangunan kilang gas Blok Masela. Saat ini, ada tiga lokasi yang dipertimbangkan.

Wakil Menteri ESDM Arcandra Tahar mengatakan, ketiga lokasi tersebut adalah Pulau Aru, Selaru dan Yamdena. “Kami bersama Inpex melihat kemungkinan di tiga daerah itu yang feasible,” kata dia di Jakarta, Kamis (25/11). Lokasi yang dipilih nantinya untuk membangun kilang pengolahan gas bumi dari Blok Masela.

Ada beberapa pertimbangan pemilihan lokasi kilang tersebut. Pertama, pertimbangan teknikal yaitu pipa untuk mengalirkan gas bumi dari Lapangan Abadi Blok Masela bisa sampai ke daerah tersebut. Kedua, lokasi itu juga bisa untuk membangun pabrik petrokimia.

Ketiga, daerah tersebut sudah dihuni oleh masyarakat sehingga memudahkan dalam pembangunan wilayahnya. Keempat, daerah atau lokasi itu memang memenuhi keekonomian proyek.

Di sisi lain, Arcandra menyatakan, pemerintah juga mulai membahas alokasi penggunaan gas hasil produksi Blok Masela. Menteri Perindustrian Airlangga Hartarto sudah mengirimkan surat kepada Menteri ESDM Ignasius Jonan agar gas dari blok tersebut dialokasikan juga untuk industri dalam negeri. (Baca: Menperin Minta Alokasi Gas Blok Masela untuk 3 Perusahaan)

Menurut dia, gas dari Blok Masela memang sudah dialokasikan untuk industri dalam negeri, seperti pupuk dan petrokimia. “Yang jelas sudah ada alokasi. Daftar untuk siapa kira-kira investor yang berminat sudah ada,” ujarnya. Namun, rencana itu masih dalam pembahasan dan belum ada kontrak jual-beli gas.

Terkait rencana pengembangan (PoD) Blok Masela, Arcandra mengatakan, masih dalam tahap pembahasan. Pemerintah masih menegosiasikan rencana pengembangan blok kaya gas di Laut Arafura tersebut dengan Inpex Corporation sebagai kontraktor.

Salah satu yang dinegosiasikan adalah syarat dan ketentuannya. Contohnya, permintaan peningkatan kapasitas produksi menjadi 9,5 juta ton per tahun (mtpa). Selain itu, usulan perpanjangan kontrak pengelolaan Blok Masela yang akan habis pada 2028. (Baca: Kementerian Energi Akan Restui Kenaikan Produksi Blok Masela)

Arcandra menargetkan, PoD tersebut bisa selesai pada kuartal pertama 2017. “Berusaha sekuat tenaga supaya cepat, kami pertahankan posisi sehingga harus win-win dalam negosiasi seperti itu,” ujarnya.
0/5000
ソース言語: -
ターゲット言語: -
結果 (英語) 1: [コピー]
コピーしました!
Ministry Of Energy Of The Boiled Three Options Location Refinery Project Masela There was some consideration of the refinery site selection, such as the technical aspects, can build a petrochemical factory, already populated, and meets keekonomian. The Ministry of energy and Mineral resources (DEMR) central location to discuss the construction of a gas refinery Masela Block. Currently, there are three locations are considered.Deputy Minister of MINERAL RESOURCES Arcandra Tahar said, the location is the third island of Aru, Selaru and Yamdena. "We see the possibilities of Inpex together in three areas that are feasible," he said in Jakarta on Friday (25/11). The selected location later to build the refinery processing natural gas from Block Masela.There was some consideration of the refinery site selection. First, technical considerations i.e. the pipe to siphon gas from the field of eternal Block Masela could get to the area. Second, it could also be to build petrochemical factory.Third, the area was already inhabited by people making it easy in the development of its territory. Fourth, area or location that does meet the keekonomian project.On the other hand, Arcandra said, the Government also began to discuss the allocation of the use of gas production Blocks Masela. Industry Minister Airlangga Hartarto has already sent a letter to the Minister of MINERAL RESOURCES so that gas from Jonan Ignatius such blocks allocated also to domestic industry. (Read: Menperin ask for the allocation of Gas to Masela Block 3 companies)According to him, the gas from the Masela Block has been allocated for the domestic industry, such as fertilizers and petrochemicals. "There's been a clear allocation. List for whom approximately interested investors are already there, "he said. However, the plan was still under discussion and no gas sale contracts.The associated development plan (PoD) Masela Block, Arcandra says, is still in the stage of discussion. The Government is still negotiating the gas rich blocks development plans in the Arafura Sea by Inpex Corporation as a contractor.The one that was negotiated terms and conditions. For example, the request for an increase in production capacity be 9.5 million tonnes per annum (mtpa). In addition, the proposed extension of the Masela Block management contract expires in 2028. (Read: The Ministry Of Energy Will Increase Production Of Restui Block Masela)Arcandra targeting, the PoD could be completed in the first quarter of 2017. "Bend over backwards so fast, we preserve the position so it must be a win-win in such negotiations," he said.
翻訳されて、しばらくお待ちください..
結果 (英語) 2:[コピー]
コピーしました!
The Ministry of Energy godok Three Options Location Refinery Project Masela

There are several reasons the choice of location of the refinery, such as the technical aspects, can build a petrochemical plant, already inhabited, and meet the economic,

Ministry of Energy and Mineral Resources (ESDM) is discussing the construction site of gas works Masela , Currently, there are three locations being considered.

Deputy Minister Arcandra Tahar said, these three locations is the island of Aru, Selaru and Yamdena. "We shared Inpex saw possibilities in the three areas that are feasible," he said in Jakarta, Thursday (25/11). The location was chosen later to build a natural gas processing plant of the Masela block.

There are several reasons the refinery site selection. First, the technical considerations that pipe to drain the gas from the Abadi field Masela can get to the area. Second, the location was also able to build a petrochemical plant.

Third, the area had been inhabited by the community so as to facilitate the development of the region. Fourth, area or location that does meet the economics of the project.

On the other hand, Arcandra states, the government also began to discuss the allocation of gas usage Masela production. Airlangga Hartanto Industry Minister has sent a letter to the Minister Ignatius Jonan gas from the block allocated also to the domestic industry. (Read: Gas Allocation Request Menperin Masela for 3 Companies)

According to him, the gas from the Masela block is already allocated to the domestic industry, such as fertilizers and petrochemicals. "Clearly the existing allocations. Register to whom roughly investors who are interested already, "he said. However, the plan was still under discussion and no contract of sale of gas.

With regard to development (PoD) Masela, Arcandra said, is still under discussion. The government is still negotiating the development plan of the gas-rich blocks in the Arafura Sea with Inpex Corporation as contractor.

The one that is negotiated is the terms and conditions. For example, demand for increased production capacity to 9.5 million tonnes per annum (mtpa). In addition, the proposed extension of the Masela block management contract will expire in 2028. (Read: The Ministry of Energy Increased Production Will Bless Masela)

Arcandra targeting, PoD can be completed in the first quarter of 2017. "Trying mightily so fast, we maintain that position should be a win-win in such negotiations, "he said.
翻訳されて、しばらくお待ちください..
 
他の言語
翻訳ツールのサポート: アイスランド語, アイルランド語, アゼルバイジャン語, アフリカーンス語, アムハラ語, アラビア語, アルバニア語, アルメニア語, イタリア語, イディッシュ語, イボ語, インドネシア語, ウイグル語, ウェールズ語, ウクライナ語, ウズベク語, ウルドゥ語, エストニア語, エスペラント語, オランダ語, オリヤ語, カザフ語, カタルーニャ語, カンナダ語, ガリシア語, キニヤルワンダ語, キルギス語, ギリシャ語, クメール語, クリンゴン, クルド語, クロアチア語, グジャラト語, コルシカ語, コーサ語, サモア語, ショナ語, シンド語, シンハラ語, ジャワ語, ジョージア(グルジア)語, スウェーデン語, スコットランド ゲール語, スペイン語, スロバキア語, スロベニア語, スワヒリ語, スンダ語, ズールー語, セブアノ語, セルビア語, ソト語, ソマリ語, タイ語, タガログ語, タジク語, タタール語, タミル語, チェコ語, チェワ語, テルグ語, デンマーク語, トルクメン語, トルコ語, ドイツ語, ネパール語, ノルウェー語, ハイチ語, ハウサ語, ハワイ語, ハンガリー語, バスク語, パシュト語, パンジャブ語, ヒンディー語, フィンランド語, フランス語, フリジア語, ブルガリア語, ヘブライ語, ベトナム語, ベラルーシ語, ベンガル語, ペルシャ語, ボスニア語, ポルトガル語, ポーランド語, マオリ語, マケドニア語, マラガシ語, マラヤーラム語, マラーティー語, マルタ語, マレー語, ミャンマー語, モンゴル語, モン語, ヨルバ語, ラオ語, ラテン語, ラトビア語, リトアニア語, ルクセンブルク語, ルーマニア語, ロシア語, 中国語, 日本語, 繁体字中国語, 英語, 言語を検出する, 韓国語, 言語翻訳.

Copyright ©2025 I Love Translation. All reserved.

E-mail: