In Sulawesi will be developed two interconnected systems, namely systems Hammer-Parigi-
Poso that will blend with Sulselrabar system to focus development
on the 150 kV system, and a system that will blend with the Tolitoli Sulut- system
Gorontalo. To evacuate power from the hydropower system Poso to Palu-Parigi, being
built 150 kV transmission. The length of the new transmission line will be built
for both the system over the period 2015-2024 is 2,444 kms to the
investment fund of about US $ 416 million as shown in Table C7.4.
Issues relating to the evacuation of a power plant Hammer 3 (2x50 MW) to Hammer system
- Poso through 150 kV substation Talise and interconnection with the system plan Sulawesi
North, then the transmission segment New Hammer - Talisa 70 kV future will
be increased voltage to 150 kV and relocate IBT 150/70 kV substation Palu from
New to GI Talise. and Tolitoli system that will blend with the system Sulut- Gorontalo. To evacuate power from the hydropower system Poso to Palu-Parigi, being built 150 kV transmission. The length of the new transmission line will be built for both the system over the period 2015-2024 is 2,444 kms to the investment fund of about US $ 416 million as shown in Table C7.4. Issues relating to the evacuation of a power plant Hammer 3 (2x50 MW) to Hammer system - Poso through 150 kV substation Talise and interconnection with the system plan Sulawesi North, then the transmission segment New Hammer - Talisa 70 kV future will be increased voltage to 150 kV and relocate IBT 150/70 kV substation Palu from New to GI Talise. and Tolitoli system that will blend with the system Sulut- Gorontalo. To evacuate power from the hydropower system Poso to Palu-Parigi, being built 150 kV transmission. The length of the new transmission line will be built for both the system over the period 2015-2024 is 2,444 kms to the investment fund of about US $ 416 million as shown in Table C7.4. Issues relating to the evacuation of a power plant Hammer 3 (2x50 MW) to Hammer system - Poso through 150 kV substation Talise and interconnection with the system plan Sulawesi North, then the transmission segment New Hammer - Talisa 70 kV future will be increased voltage to 150 kV and relocate IBT 150/70 kV substation Palu from New to GI Talise.
翻訳されて、しばらくお待ちください..