Thank you for the support and cooperation that always you give.
Refer the subject of email and there is urgent condition for supply of Steel Bar IWWI at G&A production area
With this e-mail, I need the help from:
Bp. Nanang (Material Control 2):
I ask to you for prepare one operator that who have a SIO of Crane, the operator must standby from 9pm until 12 pm on this day at unloading area of steel bar at G&A.
This operator will be do the unloading process of steel bar from IWWI vehicle to the storage due this goods will be do the cutting process on Shift 3 tomorrow morning (Based on information from Bp. Nuriyan)
To: Ibu Ade & Ibu Fetty (Risk Control)
We ask the permit for unloading process in Shift 2 this afternoon because there is urgent condition at G&A production area.
This urgent condition not come from G&A but actually come from the Vendor due the delay delivery as much as 20MT, if until tonight the goods not come to YPMI, tomorrow morning (Shift 3, Thursday, Jan 23rd) the process of production in G&A will be stop due there is no stock of raw material