Power Balance Sulbagsel System:
System Sulbagsel an amalgamation system-West Sulawesi South Sulawesi, Central Sulawesi and
Southeast Sulawesi system. The system is planned to be established in 2016 after
the project 150 kV transmission interconnection system with a system of South Sulawesi South East Sulawesi
completed including IBT 275/150 kV substation Wotu. Plan the placement of
plants in system-West Sulawesi South Sulawesi, Southeast Sulawesi, Central Sulawesi balance sought
by embracing regional balance criteria.
In order to optimize the potential of hydro power is very large and
spread out in the province of South Sulawesi, West Sulawesi, Central Sulawesi and Southeast Sulawesi, will be a lot of built
hydropower projects by private developers with a total capacity of approximately 1,580
MW and by PLN approximately 425 MW during the years 2015-2024. In addition, still
there are some other hydro power potential to be developed into a
hydropower by the private sector with a total capacity of approximately 790 MW and is currently
in the feasibility study stage. If the results of the study showed technically feasible
and economical, then this hydropower project plan can then be
developed and taken into account in the balance of power system Sulbagsel. If Sulbagsel system is the incorporation of a system-West Sulawesi South Sulawesi, Central Sulawesi and Southeast Sulawesi system. The system is planned to be established in 2016 after the project 150 kV transmission interconnection system with a system of South Sulawesi South East Sulawesi completed including IBT 275/150 kV substation Wotu. Plan the placement of plants in system-West Sulawesi South Sulawesi, Southeast Sulawesi, Central Sulawesi balance sought by embracing regional balance criteria. In order to optimize the potential of hydro power is very large and spread out in the province of South Sulawesi, West Sulawesi, Central Sulawesi and Southeast Sulawesi, will be a lot of built hydropower projects by private developers with a total capacity of approximately 1,580 MW and by PLN approximately 425 MW during the years 2015-2024. In addition, still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If Sulbagsel system is the incorporation of a system-West Sulawesi South Sulawesi, Central Sulawesi and Southeast Sulawesi system. The system is planned to be established in 2016 after the project 150 kV transmission interconnection system with a system of South Sulawesi South East Sulawesi completed including IBT 275/150 kV substation Wotu. Plan the placement of plants in system-West Sulawesi South Sulawesi, Southeast Sulawesi, Central Sulawesi balance sought by embracing regional balance criteria. In order to optimize the potential of hydro power is very large and spread out in the province of South Sulawesi, West Sulawesi, Central Sulawesi and Southeast Sulawesi, will be a lot of built hydropower projects by private developers with a total capacity of approximately 1,580 MW and by PLN approximately 425 MW during the years 2015-2024. In addition, still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If Central Sulawesi and Southeast Sulawesi system. The system is planned to be established in 2016 after the project 150 kV transmission interconnection system with a system of South Sulawesi South East Sulawesi completed including IBT 275/150 kV substation Wotu. Plan the placement of plants in system-West Sulawesi South Sulawesi, Southeast Sulawesi, Central Sulawesi balance sought by embracing regional balance criteria. In order to optimize the potential of hydro power is very large and spread out in the province of South Sulawesi, West Sulawesi, Central Sulawesi and Southeast Sulawesi, will be a lot of built hydropower projects by private developers with a total capacity of approximately 1,580 MW and by PLN approximately 425 MW during the years 2015-2024. In addition, still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If Central Sulawesi and Southeast Sulawesi system. The system is planned to be established in 2016 after the project 150 kV transmission interconnection system with a system of South Sulawesi South East Sulawesi completed including IBT 275/150 kV substation Wotu. Plan the placement of plants in system-West Sulawesi South Sulawesi, Southeast Sulawesi, Central Sulawesi balance sought by embracing regional balance criteria. In order to optimize the potential of hydro power is very large and spread out in the province of South Sulawesi, West Sulawesi, Central Sulawesi and Southeast Sulawesi, will be a lot of built hydropower projects by private developers with a total capacity of approximately 1,580 MW and by PLN approximately 425 MW during the years 2015-2024. In addition, still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If The system is planned to be established in 2016 after the project 150 kV transmission interconnection system with a system of South Sulawesi South East Sulawesi completed including IBT 275/150 kV substation Wotu. Plan the placement of plants in system-West Sulawesi South Sulawesi, Southeast Sulawesi, Central Sulawesi balance sought by embracing regional balance criteria. In order to optimize the potential of hydro power is very large and spread out in the province of South Sulawesi, West Sulawesi, Central Sulawesi and Southeast Sulawesi, will be a lot of built hydropower projects by private developers with a total capacity of approximately 1,580 MW and by PLN approximately 425 MW during the years 2015-2024. In addition, still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If The system is planned to be established in 2016 after the project 150 kV transmission interconnection system with a system of South Sulawesi South East Sulawesi completed including IBT 275/150 kV substation Wotu. Plan the placement of plants in system-West Sulawesi South Sulawesi, Southeast Sulawesi, Central Sulawesi balance sought by embracing regional balance criteria. In order to optimize the potential of hydro power is very large and spread out in the province of South Sulawesi, West Sulawesi, Central Sulawesi and Southeast Sulawesi, will be a lot of built hydropower projects by private developers with a total capacity of approximately 1,580 MW and by PLN approximately 425 MW during the years 2015-2024. In addition, still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If Sulteng pursued balanced by embracing regional balance criteria. In order to optimize the potential of hydro power is very large and spread out in the province of South Sulawesi, West Sulawesi, Central Sulawesi and Southeast Sulawesi, will be a lot of built hydropower projects by private developers with a total capacity of approximately 1,580 MW and by PLN approximately 425 MW during the years 2015-2024. In addition, still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If Sulteng pursued balanced by embracing regional balance criteria. In order to optimize the potential of hydro power is very large and spread out in the province of South Sulawesi, West Sulawesi, Central Sulawesi and Southeast Sulawesi, will be a lot of built hydropower projects by private developers with a total capacity of approximately 1,580 MW and by PLN approximately 425 MW during the years 2015-2024. In addition, still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If still there are some other hydro power potential to be developed into a hydropower by the private sector with a total capacity of approximately 790 MW and is currently in the feasibility study stage. If the results of the study showed technically feasible and economical, then this hydropower project plan can then be developed and taken into account in the balance of power system Sulbagsel. If
all the hydro power potential is developed, there will be an additional
capacity of about 2,800 MW of hydropower in total.
In addition to the potential for hydro power, wind power potential in South Sulawesi large enough
also be utilized for power generation (commonly called thermal power station)
which is connected to the Grid Sulawesi, but not taken into account in the balance of
power for intermittent / continuous no.
Power hydropower and thermal power station capable of greatly influenced by the season so it needs to
be anticipated by building another plant that can cover
the power shortage during the dry season for hydropower, and when there was no
wind for a thermal power station.
Projection needs load and generation additions in the system plan
Sulbagsel year period 2015-2024 as contained in the balance of power
in accordance Table 6:26. During this period, planned to be built
a new plant with a total capacity of 4,357 MW with a reserve
margin (RM) ranged between 32% smpai 53% except for 2015 and 2017
below 30%.
翻訳されて、しばらくお待ちください..
